Civic Centre project update – June 2024
Throughout June work on the two arenas in the Civic Centre continued, including painting, dressing rooms for the spectator arena, and the installation of roof top mechanical units to provide ventilation and dehumidification for both arenas. Crews also started framing and mechanical rough ins for the concourse level washrooms.
On the exterior of the building, concrete curbs were installed on the north side of the facility and grading was done in the west parking area. Bases for the lights in the west parking lot have also been installed.
The south side of the facility that will be home to the branch of the Spruce Grove Public Library, art gallery, black box theatre and lobby started to take shape in June. Reinforcing rebar for some of the floors has been installed and the concrete slab for the theatre was poured. Exterior studs and sheathing for the library, gallery, and theatre are also under way.
There continues to be an average of more than 100 workers on site each day. Check out the monthly one-minute timelapse for June and see the progress for yourself!