Construction Projects
Each year the City of Spruce Grove undertakes a range of construction projects to support and enhance community growth, development and safety for both residents and visitors. This can include the regular maintenance or replacement of existing infrastructure, as well as the addition of new features or amenities.
Information about this year’s construction projects can be found below, including impacts related to roadways, utilities, buildings, parks and facilities. We understand that construction can impact the community and we thank you for your patience while we complete this work.
Current projects
The Harvest Ridge stormwater facility requires upgrades to repair the elevation of sediment settlement, algae build up, and drainage limitations. The repairs will be phased to accommodate the necessary weather restrictions required for completing upgrades.
During construction residents may experience detours along the trail near the stormwater facility, notice construction equipment in the area, and experience additional noise.
Once upgrades are complete, the facility will be deeper to improve capacity and should produce less odours.
Project timeline:
Facility upgrades will begin in May 7, 2024 and are scheduled to be completed by the end of August (weather permitting).
Project status:
Complete
Improvements to the drainage easement will be completed along Diamond Avenue in the industrial area of Spruce Grove. The project will have minimal disruption to local businesses.
Project timeline:
July
Project status:
Complete
Resurfacing work on Highway 16A will continue in 2024 on the westbound lanes from the east end of the City to Century Road. The work will be predominately completed at night to reduce impacts to residents and businesses.
Project timeline:
Anticipated: July 15 to 25
Project status:
Complete
Project description:
Following two years of significant construction in the City Centre area, the focus this year will be completing all improvement work and adding greenery to the streetscape on McLeod Avenue and Main Street. Work will also include surface upgrades on Calahoo Road from Mohr Avenue to Highway 16A, and on First Ave South. Some underground work will be completed on Mohr Avenue adding capacity to the water and sanitary lines in preparation for Meridian Housing’s seniors living facility.
Project timeline:
Improvements and landscaping on Main Street and McLeod Avenue to be completed in late summer 2024.
Calahoo Road and Mohr Avenue is anticipated to start in August and end late summer 2024.
Project status:
2024 work complete
Industrial watermain replacement is scheduled along Madison Crescent. Disruptions in the local area should be anticipated. Effected businesses will be contacted prior to construction.
Project timeline:
June 19 to October
Project status:
Complete
The City of Spruce Grove receives its potable (drinkable) water from the Capital Region Parkland Water Services Commission through a watermain that comes from Edmonton and extends to Stony Plain. In 2024 the Commission is upgrading the watermain to ensure the ability to provide adequate water supply to the growing population in the Parkland area.
In tandem with the Commission project, the City will be undertaking work to construct a new water fill building with connections to two existing reservoirs and connecting to the newly upgraded Commission watermain.
The water fill building will be constructed on a section of the parking lot at Henry Singer Park and will impact groups that use the baseball diamonds and pickleball courts located at the park. A portion of the parking lot will be blocked off for construction laydown and work, and there will be construction activity present that will create noise and potentially produce dust. Users are encouraged to carpool when possible.
Once complete, this work will ensure the ability to provide adequate water supply to the growing population in the area.
Project timeline:
Construction is expected to start summer of 2024 and will be ongoing through winter of 2025.
Project status:
Ongoing
The City of Spruce Grove is undertaking a multi-year project to revitalize and enhance Central Park. This project will add new amenities, such as skate park, pump track, a bike track, a playground, picnic tables and benches, while also retaining key features like the skating oval, splash pad, treed area and log cabin.
During construction, Central Park will remain open, but some areas may be temporarily inaccessible. There will also be construction vehicles in the area and noise and dust will be increased. Traffic may be affected along King Street and Agrena Road.
Project timeline:
Spring 2024 to summer 2025.
Project status:
2024 work complete
Infrastructure improvements west of the McLeod Avenue and Jennifer Heil Way intersection are needed to accommodate future planning in the area south of Legacy Park. To complete these improvements, a temporary road will be built to accommodate a short-term road closure, which is anticipated to start July 22.
The planned construction work will then improve existing neighbourhood access in Legacy Park and connect municipal services to the proposed residential land south. Upgrades include improvements to the storm sewer system, underground infrastructure, and local road.
These neighbourhood access improvements will be completed along the section of road west of Jennifer Heil Way on McLeod Avenue in three phases.
- Stage one includes the building of a temporary road south of McLeod Avenue. Work started on June 18 and is anticipated to be completed by July 21.
- Stage two includes the closure of the McLeod Avenue roadway to upgrade underground infrastructure and complete road upgrades. Traffic is anticipated to be redirected to the temporary road starting July 22 until mid-September. Vehicles will need to exit south on Jennifer Heil Way and enter the neighbourhood by travelling south past the permanent McLeod Avenue entrance. No left turns will be available during this stage.
- Stage three includes the reopening of McLeod Avenue mid-September and the completion of the remaining infrastructure upgrades. Infrastructure work will include median upgrades and temporary road closures along Jennifer Heil Way and Highway 16A.
Please watch for signs in the area and follow directions.
Project timeline:
Phase 1 construction: June 18 – July 21
Phase 2 construction: July 22 – mid-September
Phase 3 construction: mid-September – October
Project status: Complete
Watermain inspections will take place between the City’s two water reservoirs for maintenance purposes.
To support this inspection work, travel delays southbound on Calahoo Road, between Grove Drive and Highway 16A, should be expected due to rolling temporary lane closures.
- August 12: Inspections will start at location one, moving northbound to location two, and ending at location three. Traffic will be limited to one lane due to rolling temporary southbound lane closures between 7:15 a.m. and 5 p.m.
- August 13: All three inspection points will be simultaneously reviewed between 9 a.m. and 12:30 p.m. Southbound travel will be limited to one lane.
- August 14: All three inspection points will be simultaneously reviewed between 11:30 a.m. and 2 p.m. Southbound travel will be limited to one lane.
Project timeline:
Watermain inspections are anticipated to be completed between August 12–14, 2024.
Project status:
Complete
Neighbourhood upgrades will be ongoing in the Fenwyck neighbourhood east of Pioneer Road. Work includes:
- Paving of Grove Drive east of Pioneer Road to connect Grove Drive and Fenwyck Boulevard.
- Median upgrades at Pioneer Road and Fenwyck Boulevard. East bound traffic on Fenwyck Boulevard is anticipated to be redirected to Brunswyck Crescent from Oct. 15-25.
Project timeline:
Spring - Fall, 2024
Project status:
Complete
Starting Thursday, September 19, a temporary trail closure can be expected in the McLaughlin neighbourhood due to construction in the area. The trail is anticipated to the by November.
Project timeline:
September 19 to the end of October
Project status:
Complete
Intersection upgrades will be completed at Century Road and Grove Drive to improve traffic flow. Upgrades include an additional southbound turning lane on Century Road going east towards Grove Drive, and intersection traffic light upgrades. Traffic disruptions and rolling lane closures should be expected in the area.
Project timeline:
September 21 & October 19 – November 4.
Project status:
Complete
Maintenance work on Century Road from Century Close to southern city limits will take place to increase mulch in the ditches along the roadway. Temporary lane closures should be expected.
Project timeline
September 30 – October 2
Project status
Complete
Crosswalk equipment including crossing signals, poles and bases will be replaced at the King Street and Fifth Avenue crosswalk. The crosswalk will be closed for the duration of work and pedestrians will need to use alternative crossings.
Project timeline
Nov. 21 - Dec. 18
Project status
Scheduled
Partnered projects
Work will continue on the connecting trail between Spruce Grove and Stony Plain to make commuting between the two communities more accessible and safer for those using alternate modes of transportation.
This trail is located on the south side of Highway 16A, between Veterans Boulevard and Campsite Road. The Town of Stony Plain will be completing the portion on the south side of Highway 16A.
Project timeline:
2023 – 2024.
Project status:
Complete
Grand opening event:
- Date: Monday, September 16, 2024
- Time: 2 p.m.
- Location: South of Highway 16A (parking available at Rotary Centennial Park, Spruce Grove).
Related projects
Project description:
Atco Gas is expanding their existing infrastructure located on Century Road just south of Brookwood Drive. Construction work will affect both drivers and pedestrians, and traffic will be reduced to one lane going southbound on Century Road. The local pathway will be closed and pedestrians are asked to use the paved alley.
Speed will be limited to 40 kilometers per hour throughout the construction area.
Project timeline:
March 18 – end of May/mid-June.
Project status:
Complete
CN Rail will be completing railway crossing upgrades at the railway intersection at Campsite Road and Golden Spike Road. Drivers can expect temporary one-day road closures at the railway crossings and will need to access local businesses via alternate routes.
Project timeline:
Thursday, September 12, from 9 a.m. to 3 p.m., at Campsite Road.
Tuesday, October 15th from 10 p.m. to Wednesday, October 16 at 10 a.m., at Golden Spike Road.
Project status:
Complete
The Capital Region Parkland Water Services Commission is upgrading a watermain that runs from Edmonton and extends through Spruce Grove to Stony Plain. Construction work in Spruce Grove will be on South Avenue, Alberta Avenue, and Madison Crescent.
A temporary lane closure will be in effect along South Avenue from Shep Street to Golden Spike Road starting Tuesday, September 3 and will be ongoing until the end of the month.
Local traffic will be impacted. Please follow all signage.
Project timeline:
Spring/summer 2024 and 2025.
Project status:
2024 work complete
Transportation and Economic Corridors is currently undertaking a functional study of the 22.5 kilometres stretch of Highway 16A between the Anthony Henday and Highway 779. The study is evaluating expanding the highway from two lanes to four lanes in both directions.
A drop-in open house was held on June 12, 2024, at the Parkland Village Community Centre, #60 53222 RR 272, Spruce Grove, AB.
Questions?
For any inquires related to any of the construction projects listed above, please contact engineering@sprucegrove.org.
Regular maintenance
In addition to larger construction projects, City crews also conduct regular maintenance and repairs on streets and sidewalks throughout the community, including:
- Crack sealing
- Street sweeping
- Line painting
- Pothole repairs
- Asphalt repairs
- Concrete repairs and maintenance
- Traffic light repairs and maintenance
- Drainage maintenance
Reminder: please slow down!
When driving through construction zones, drivers are reminded to slow down, obey all posted speed limits, and watch for portable traffic signs or flag people who may be in place to manage traffic flow. And please give crews room to work so everyone can get home safely at the end of the day.